Find help with pool and spa barrier inspections for Melbourne properties.

Barrier non-compliance, Form 24 and re-inspection

When a Victorian pool barrier fails: the 60 day notice, when Form 24 is issued straight away, council's barrier improvement notice and the re-inspection.

When a Victorian pool or spa barrier fails inspection, the inspector usually gives the owner a written notice listing the defects, a deadline of no more than 60 days and a time to come back. If the barrier is fixed by then, a certificate of barrier compliance (Form 23) is issued. If it is not, or if the fault is serious, the inspector issues a certificate of barrier non-compliance (Form 24), lodges it with council, and council’s municipal building surveyor takes over. Owners who need repairs organised or a re-inspection booked can use this site to reach independent registered practitioners; the provider sets the scope and price.

Illustrative photo for Barrier non-compliance, Form 24 and re-inspection

How the two paths compare

Written notice from the inspector Immediate Form 24
When it is used Defects that can be fixed within the notice period Serious or unfixable faults (listed below)
Time to fix Set in the notice, up to 60 days No grace period from the inspector
Who lodges paperwork You lodge the Form 23 after a pass The inspector lodges Form 24 with council and gives you a copy
Council fee Ordinary certificate lodgement fee A much higher non-compliance lodgement fee, set by the state
What follows Re-inspection, then Form 23 Barrier improvement notice or a building notice or order

The City of Melbourne publishes both lodgement fees, and the non-compliance fee is many times the compliance one. That gap is the main reason to fix defects inside the notice period.

When must the inspector issue Form 24 straight away?

According to the Building and Plumbing Commission (BPC), the inspector must issue a certificate of barrier non-compliance immediately if:

  • the barrier cannot be made compliant, or the owner is unlikely to make it compliant within 60 days
  • the barrier poses a significant and immediate risk to life or safety
  • a gate or door, when closed, can be opened by someone who cannot reach the opening mechanism
  • a gate or door in the barrier cannot be completely closed
  • any part of the barrier is below its required height, measured from the ground on the approach side

What happens at the re-inspection?

The inspector returns at the time set in the notice and checks each listed defect. If everything is fixed, you get a Form 23 and lodge it with council within 30 days. If some defects remain but the inspector is satisfied you are making progress, the BPC says they may allow seven more days. Otherwise a Form 24 is issued.

hipages publishes a national average of $120 for a second inspection. Some inspectors include one re-inspection in the first quote; others charge each visit separately. Ask before you book. The cost guide sets the inspection and repair ranges side by side.

What council does after a Form 24

Once council receives the certificate of barrier non-compliance, the municipal building surveyor issues either:

  1. A barrier improvement notice (Form 25). Usually for minor defects. It states what to fix and by when. You then need a re-inspection and a Form 23 lodged before the deadline.
  2. A building notice or order under the Building Act 1993. Used where the surveyor considers it appropriate for the nature of the fault.

The BPC says missing the deadline in a barrier improvement notice can bring an on-the-spot fine, and not lodging the compliance certificate by the deadline can bring a further fine.

Which defects are most often on the notice?

These are the defects that come up most. Several of them are on the list of things Consumer Affairs Victoria asks renters to check:

  • gates that do not self-close from every open position, usually tired hinges or a gate that has dropped
  • latches that no longer catch, or sit where a small child can reach them
  • pot plants, pool pumps, barbecues or branches close enough to climb
  • timber boundary palings that are loose, rotten or easy to climb
  • soil, mulch or paving built up against the fence so the height on the approach side is now too low
  • gaps at the bottom of the fence where ground has washed away

Most of these are maintenance. Some are not: the BPC says replacing or altering barrier posts or footings, including on a boundary fence, needs a building permit. The pool gate and fence repairs page sets out which repairs need one.

Order of work that keeps the deadline

  1. Read the notice and list each defect with its location.
  2. Fix the quick items yourself the same week: move climbable objects, trim plants, rake back soil.
  3. Get repair quotes for hardware, panels or posts, and ask each repairer whether the work needs a building permit.
  4. Book the re-inspection for a date after the repairs and before the deadline.
  5. Lodge the Form 23 within 30 days of receiving it.

What a careful inspector will not do

  • Pass a barrier on a promise that the repair will be done later.
  • Extend the time beyond what the regulations allow.
  • Sell you the repair work as a condition of the re-inspection. If the same business offers both, ask for separate written quotes.

If you have already received a barrier improvement notice

Check its deadline and when the re-inspection has to happen before it. Owners in Bayside can apply to council for an extension of time to lodge a certificate of barrier compliance; other councils have their own process, so ask your council early rather than after the date passes. For local contacts see Doncaster in Manningham or Berwick in Casey.

Next step

Have the notice or Form 24 in front of you and request a re-inspection or repair quote, listing each defect and the deadline.

Send a job enquiry

Frequently asked questions

How long do I have to fix defects after a failed inspection?

The inspector's notice sets the deadline, which can be no more than 60 days. If you have made real progress but are not finished, the inspector may allow up to seven more days before deciding.

Who sends the certificate of non-compliance to council?

The inspector lodges it with council and gives the owner a copy. Council then notifies you of the lodgement fee and the municipal building surveyor decides on the next step.

What is a barrier improvement notice?

A notice from council's municipal building surveyor, usually for minor faults, telling you what to fix and by when. You then need a registered inspector to check the barrier and a compliance certificate lodged before that deadline.

Can I use a different inspector for the re-inspection?

The notice names the date and time the issuing inspector plans to come back. If you would rather use someone else, ask the original inspector and your council how that affects the notice before you book anyone new.

Will I be fined for a failed inspection?

Failing an inspection is not itself a fine. Fines can follow if you do not register the pool, do not lodge a certificate by the due date, or do not comply with a barrier improvement notice in time.